Project Lead: Jack Berry
Project Summary: Jack Berry of Berry Consulting successfully cleaned and disinfected a 24-inch ductile iron water supply line following a storm that deposited debris into the pipeline. The project was completed on time, on budget, and allowed for the supply line to be brought back into service.
Challenge: A sudden storm washed several yards of debris into a 24-inch ductile iron water supply line. Traditional flushing methods would have required significant water flow (20,000 to 30,000 gallons per minute) for several minutes, potentially causing damage to the pipeline.
Solution: Jack Berry devised a plan to clean and disinfect the pipeline using a series of four poly pigs (cleaning devices) pushed through the line with 200 gallons per minute of flushing water treated with pool shock (NSF 61 certified).
Process:
Benefits:
Project Lead: Jack Berry
Project Summary: Jack Berry successfully cleaned and disinfected a newly installed 8-inch ductile iron water supply line. Traditional cleaning methods, including multiple flushings, chemical injections, and tests, had failed.
Challenge: Despite multiple cleaning attempts, the new water supply line remained unclean. Traditional methods were ineffective, requiring Jack Berry's intervention.
Solution: Jack Berry devised a plan to clean and disinfect the pipeline using eight poly pigs (cleaning devices) pushed through the line with less than 200 gallons per minute of flushing water treated with pool shock (NSF 61 certified). He also secured approval from the water district for an 8-inch hydrant branch to launch the pigs.
Process:
Benefits: